Sulaibiyah Housing Project Print E-mail
Contract Value:
K.D 54,000,000
Completed On: 1979
Client: National Housing Authority - Kuwait
Consultant: Associated Consulting Engineers - UK
This project had 5554 semi-attached one-storey houses, 100 transformer structures, roads, and services.

The work was to be completed within 30 months which required unique programming and follow-up.

The job was completed on time and most satisfactorily for all concerned parties.
 
 